Applecross Alchera Living

Applecross Village provided affordable housing for people aged 55 and over who could live independently. The village was at 750 Canning Highway in Applecross and had 24 one- and two-bedroom units. Residents shared laundry facilities and held regular get-togethers at the Social Centre.

 

When the village was built

The City of Melville Aged Persons’ Trust built the village in 1986-87. The City supplied the land and the Trust paid to build the units. Lot 5, which the council referred to as Lot 5 Collier Street in its sale plan, covered 3,935m² and made up most of the village. The village itself was listed under its Canning Highway address.

 

The Trust had already opened the first stage of Weeronga Village in Willagee in 1975 and built Bull Creek Village in 1984. The City’s financial report records 1 February 2008 as the date the Trust changed its name to Alchera Living.

 

Alchera buys the land

In November 1992, the council agreed to transfer land at the Applecross and Bull Creek villages to the Trust at no charge, with the Trust paying the transfer costs. Under that arrangement, the assets would have gone back to the City if the Trust was wound up. The council later rescinded that decision and dealt with the two lots as a sale.

 

By June 2009, the Applecross lot had been valued at $2 million. In 2011, Alchera offered $4.5 million plus GST for both lots. The City’s accounts recorded $1.875 million for Lot 5 at Applecross and $2.625 million for the Bull Creek lot. The Applecross figure was for the main parcel of land Alchera was located on.

September 2025

Update

I spent another hour or two looking for more information on Alchera Living’s Applecross Village. I tried a heap of different sources and keywords and it’s ridiculous how little I could find. There are a few references to the units and the sale of the land in 2011 but very little about the village itself. I still haven’t found a demolition permit or a development application for the site.

 

Like so many places around Perth, once it’s gone, you could search the address and barely know it had ever been there.

September 2025

Applecross Shore Aged Care

The facility was built across two former aged care properties at 30 Carron Road and 45A Canning Beach Road. The redevelopment was called Opal Applecross in the planning and construction records. The completed facility is known as Applecross Shore Care Community.

 

From partial demolition to a full redevelopment

The first development application was lodged with the City of Melville on 22 January 2018. Opal proposed a 150-bed aged care facility that would replace part of the existing premises and retain the northern wing of Carron House. The Metro Central Joint Development Assessment Panel approved the application on 16 April 2018.

 

Opal later proposed demolishing and replacing the northern wing as well. In a letter to neighbours, the company said the existing and proposed buildings had different floor levels and there was limited space to connect them. It had also secured funds for a full redevelopment. T&Z Architects revised the overall floor plans for the development application on 25 February 2019 and issued the drawing set for a design development report on 1 March 2019. The panel approved the northern wing redevelopment on 18 March 2019. The City of Melville later described the approved facility as a three-storey building with 136 rooms across its northern and southern wings, with allied health consulting rooms on the ground floor.

December 2020

How the building was laid out

T&Z Architects divided the floor plans into three connected sections, labelled Blocks 1, 2 and 3. The main entrance was off Riverway, where vehicles could pull up under a covered drop-off. Inside, the foyer led to reception, interview rooms and a café. The ground floor also had a lounge with a fireplace, a dining room, a salon or day spa and an activity room. A courtyard beside the link between Blocks 1 and 3 included a reflection pool.

 

All 20 ground-floor resident rooms were in Block 2. Each had its own ensuite, and the rooms were arranged along corridors on either side of an internal courtyard. A nurse station and medication room were nearby. Parking was shown under part of Block 2, with a separate car park and drop-off next to Block 3.

 

Block 3 had its own health foyer and allied health area. The plans also label a pool room, a staff room and deck, lockers, a maintenance workshop and two fire water tanks. The main kitchen was in Block 1 behind the dining and café areas, with its own cool room, freezer, dry store, scullery and dishwashing area. Separate washing and drying rooms and linen and bin chutes were also shown on the plans.

 

The two upper floors contained single, premium and companion rooms, along with suites. Some suites had a separate lounge, and selected rooms had balconies. Both floors had shared lounges, dining and activity rooms, as well as nurse stations and medication rooms. The uppermost floor also had a clinical manager’s office and a training room. One balcony was drawn with solid privacy screening 1.8 metres above the finished floor. Two lifts and five numbered stairways linked the building’s three levels.

February 2021

Geotech Report

Douglas Partners returned to the site on 26 April 2019 after an earlier investigation in October 2016. The engineers drilled three shallow boreholes, carried out four cone penetration tests and ran two tests to measure how quickly water would soak into the ground. The deepest test reached 19.1 metres.

 

At most test locations, sand and sandy gravel fill extended 0.6 to 3.1 metres below the surface. Beneath it was natural sand that generally became denser with depth. At two locations, the sand gave way to silty sand and sandy silt at 15.7 and 17.2 metres. Groundwater was recorded between 1.6 and 2.3 metres below the surface in the four cone test holes that day.

 

A 20-metre-long, two-metre-deep infiltration system was proposed for the north-west corner of the site. It was intended to return water pumped out during construction back into the ground on site.

May 2021

The tower crane

The tower crane was installed on 5 September 2020 and dismantled on 11 September 2021, just over a year later. It was a Potain MR225 luffing-jib tower crane manufactured in 2006, with the serial number 405014. The inspection report lists a freestanding mast height of 32.5 metres and a maximum working radius of 54.9 metres. The crane could lift up to seven tonnes at shorter radii and was rated to lift 2.05 tonnes at its full reach.

 

Belpile certified the crane base piling design for BGC Construction on 28 January 2020. The design called for four piles, each 600 millimetres in diameter, and drew on the Douglas Partners report and Belpile’s own ground testing. WorkSafe registered the design on 12 March 2020 under WAC22496.

 

ELC inspected the crane on 16 September 2020, 11 days after it went up. The stability test used a 2,345kg load at a radius of 54.9 metres, and the dynamic test used 7,710kg at 14.1 metres. The inspector recorded no faults requiring rectification and noted minor rust and scale on the mast and jib for monitoring during servicing. On 1 October 2020, WorkSafe registered the individual crane to FG Cranes Pty Ltd at the Applecross site under WC21216.

August 2021